I bought most of the hardware from the usual spot, Home Depot, but the wood and Trex decking were much less expensive at Berco Redwood. I used screws for everything, so there are no nails in this deck. I lost a week by buying the deck late on a Saturday so it couldn't be delivered until Monday. All I could do was move the decking to the back patio Monday night after work. Then look at it all week wishing I could start getting some of it down.
The first weekend attaching the decking was a cold one so I wasn't moving as fast as I would have liked. I was getting 5 rows of deck done a day. The following Saturday I finished the decking on the front side. Once I finish the far side I'll cut and attach the trim around the outside. The trim will cover the pressure treated wood still visible around the outside of the deck.
The framing is done and all I have left to do is finish attaching the decking (and cast a step on each side). I'll have additional progress photos posted soon. I've been using the film camera for most of the shots.